Author: xlmsmartcity

LED smart lights Phase II

Pearl Beach Road development and Kisok shop arrangemnets

Categories
Completed Projects

Pearl Beach Road development and Kisok shop arrangemnets

  • Name of the Project: Pearl Beach Road development and Kisok shop arrangemnets
  • Project cost (Rs.in Cr): 0.94
  • Description:
    “The following improvements are programmed under smart city scheme for the effective use of public a) Providing CC pavements at Scatting yard b) Construction of Strom water drain at North beach road c) Providing Kiosk shop at Pearl beach d) Improvement of Pearl beach at North beach road”
  • Physical Progress: 100%
  • Project End Date: 30 Jun 2020

Muthu Nagar Beach LED Fittings,providing UG cables and Highmast Light arrangements

Categories
Completed Projects

Muthu Nagar Beach LED Fittings,providing UG cables and Highmast Light arrangements

  • Name of the Project: Muthu Nagar Beach LED Fittings,providing UG cables and Highmast Light arrangements
  • Project cost (Rs.in Cr): 0.59
  • Description:
    By securing the Muthu Nagar Park for the convineance of public entertinment including safety measures.
  • Physical Progress: 100%
  • Project End Date: 30 Nov 2019

Smart Water Supply –Improvement of existing D system

Solar Roof Top

Categories
Completed Projects

Solar Roof Top

  • Name of the Project: Solar Roof Top
  • Project cost (Rs.in Cr): 1.58
  • Description:
    “It has been proposed to instal Solar Roof Top Power System in Corporation owned buildings which are having single phase and three phase service connections.Totally 227.50 KW Capacity has been Proposed to implement the installation of Solar Roof Top System. Totally 21 buildings proposed and in 19 locations are in execution. 14 Nos office buildings and 7 Nos Corporation School buildings are provided with Solar Photovoltaic Modules and Inverter pannels .”
  • Physical Progress: 100%
  • Project End Date: 30 Nov 2021

Construction of SWD- TNSUDP

Open Space making – 9 parks

Categories
Completed Projects

Open Space making – 9 parks

  • Name of the Project: Open Space making – 9 parks
  • Project cost (Rs.in Cr): 4.06
  • Description:
    The following provision are made in compound wall security room, Toilet arrangements lighting facilities, sitting benches, foot path, play field arrangement Green space Traffic Rules and Regulations Material arrangements and water supply arrangements etc.,
  • Physical Progress: 100%
  • Project End Date: 31 Dec 2020

Redevelopment of Smart Anganwadi

Renovation of Burial Ground

Categories
Completed Projects

Renovation of Burial Ground

  • Name of the Project: Renovation of Burial Ground
  • Project cost (Rs.in Cr): 4.52
  • Description:
    It is proposed to construct Shed and Security Room at Burial Ground in Thoothukudi Smart City. It has a overall area 115396.28 Sq.m, Compound wall of overall length 1507.83 m is proposed around the burial ground. Partial Brickwork and grillwork is proposed between the columns 4 m c/c. A road is proposed behind the burial ground connecting the two roads on the left and right of the burial ground. The proposed road is found to have an extent of 2225 Sq.m. 15 No’s of Entrance arch is provided in each and every entrance. 8 No’s of shed each of 75 Sq.m area is proposed. 11 No’s of security room each having an extent of 4 Sq.m is provided in each Gates.
  • Physical Progress: 100%
  • Project End Date: 28 Feb 2021

Conversion of LED Street Lights

Categories
Completed Projects

Conversion of LED Street Lights

  • Name of the Project: Conversion of LED Street Lights
  • Project cost (Rs.in Cr): 14.41
  • Description:
    It has proposed 14920 Nos conversionallights in to 14496 Nos LED Lights as per the IGA report, CCMS – 1 No, Single Phase street light controller – 825 Nos, Primeted connector – 14500 Nos, Single phase service EB meter Box – 225 Nos,Three Phase Service 4 X 35 sqmm all cable – 225 mtrs.
  • Physical Progress: 100%
  • Project End Date: 31 Dec 2021