Construction of Storm Water Drain –ABD area – Phase II

Name of the Project: Construction of Storm Water Drain –ABD area – Phase II

Project cost (Rs.in Cr): 81.36

Description:

“1. Providing total length of 4711m of Storm Water Drain Along south cotton road (Joins to George Road), Drain along North Raja Street, Drain Along East Coast Road joins to Sea, Along Victoria Extension road & Branch Joined to George Road (Left & Right side of Road), Along Devispuram Road to Buckal Canal, Joins to SBI colony main Drain and Along Devispuram and Disposed to Buckal Canal . 2.Providing total length of 6974m of Strom Water Drain Along cross road from Palayamkottai road to Buckal Canal, Teachers Colony and Disposed Buckal Canal, Teachers Colony Main Road and Disposed to Buckal Canal, Along Millerpuram Main Road and Disposed to Buckal Canal, Along TMB Colony Main Road and Disposed to Buckal Canal, Along Millerpuram East Main Road and Disposed to Buckal Canal. 3.Providing total length of 7010m of Strom Water Drain from New colony to Sea (Via George Road road), Geetha Jeevan Nagar to Sea “

Physical Progress: 95%

Project End Date: 30 Apr 2022