Skip to the content
Construction of Resource Recovery Centre at kathirvel nagar
- Name of the Project: Construction of Resource Recovery Centre at kathirvel nagar
- Project cost (Rs.in Cr): 2.07
- Description: “RRC – Resource Recovery Centre 2 to 2.5 Tons of waste can be segregate in the RRC per day Provisions : Batching Maching, Weighing Machine, Segration Mation, Incinator, Type of Materials can be Segregate : Cloths, Brass Materials, Wooden Materials, Rubber Materials, E-Waste Materials, Metals items, Glass materials, Plastic Materials, Bags, Bottle, Cheppls etc,.”
- Physical Progress: 44%
- Project End Date: 31 Mar 2022