Name of the Project: Proposed Centralised SCADA system demand driven-Water Supply & Distribution Management System for the TCMC Water Supply Improvement Scheme
Project cost (Rs.in Cr): 8.47
Description:
84 MLD of raw water from Intake Well located at 100m away from upstream of Maruthur Dam at Kaliyavoor in River Thamirabarani being pumped to the Water Treatment Plant at Keelavallanadu, with the supporting of 4 nos of 600HP/450KW Vertical Turbine Pump sets. It is designed to operate 2 Nos of 600HP Vertical Turbine Pump sets parallelly at a time to pump as per the designed quantity of 84 MLD raw water from the existing source. The pumped raw water conveyed through size of 1100mm dia SWMS pipe to Water Treatment Plant at Keelavallanadu for a distance 10.85Km.From the Water Treatment Plant at Keelavallanadu, the treated clear water will be gravitated to the beneficiaries of TCMC limit. The clear water transmission main of size 1200mm dia SWMS pipe is laid for the distance of 25 Kms with the provision of sufficient sluice valve / scour valve arrangements. According to the design of the project, the treated clear water is being feed through 30 Nos OHTS comprises 13 Feeder Main and segregated to 30 Zones.
Physical Progress: 65%
Project End Date: 31.03.2022
Name of the Project: Flood mitigation -SWD-Phase-III – (Packages –I,II,III &IV)
Project cost (Rs.in Cr): 47.61
Description:
Storm water Drain construction will reduce the Stagnation of rain water . City will be clean .
Physical Progress: 65%
Project End Date: 31 May 2022
Name of the Project: Smart Road
Project cost (Rs.in Cr): 68.59
Description: “1. Cement concrete pavement with random rubble median, two wheeler and four wheeler parking. Geometric improvement in major intersection, footpath for pedestrian, Street light arrangement, New trees, grating around trees, landscaping, Planter box in footpath wherever applicable, dust bin, Water line and Electric line facilities will be provided. 2. High strength so as to distribute the wheel load of the vehicles to the bottom layer’s without any deformation. 3. Resistance to abrasion caused by the tyres. 4. Should minimize skidding of vehicles. To achieve the above the concrete should be strong, hard and durable. Thus PQC is a special grade of Concrete suitable for highway “
Physical Progress: 48%
Project End Date: 31 Mar 2022
Name of the Project: Smart Bus Depo for TNSTC at New Bus stand
Project cost (Rs.in Cr): 9.41
Description: “It is Proposed to construct TNSTC Depot Building with overall area of 1.94 acres with maintaince shed in the ground floor, Regional office in the second floor, Divitional office at second floor with restricted access ladies dormitory with capacity of 25 persons, Dormitory building for male staff with 200 person capacity in the third floor, kitchen cum dining hall has been provided with dormitory and separate recreational club ha been provided for mal and female staff. “
Physical Progress: 67%
Project End Date: 31 May 2022