- Name of the Project: Roach Park & Beach Road development and Associated Tourism Development
- Project cost (Rs.in Cr): 1.65
- Description:
“The following improvements are programmed under smart city scheme for the effective use of public a) Providing 30m High masts at Muthu nagar beach b) Providing of new underground cable at Muthu nagar beach c)Providing LED lighting in Muthu nagar beach d) Providing CC pavements at Scatting yard e) Construction of Strom water drain at North beach road f) Providing Kiosk shop at Pearl beach g) Improvement of Pearl beach at North beach road h)Providing of BT surface for cycle track of south beach road(Roach park to Boat jetty) “ - Physical Progress: 100%
- Project End Date: 25 Jan 2021
Roach Park & Beach Road development and Associated Tourism Development
LED smart lights
Categories
LED smart lights
- Name of the Project: LED smart lights
- Project cost (Rs.in Cr): 1.82
- Description:
To construct the formation of orderly lighting arrangements in the traffic roads with eco friendly energy savings LED light and reduce the lighting polution. - Physical Progress: 100%
- Project End Date: 31 Dec 2021
Container Box Toilet -10 Nos
Categories
Container Box Toilet -10 Nos
- Name of the Project: Container Box Toilet -10 Nos
- Project cost (Rs.in Cr): 0.49
- Description:
“By providing container type toilets in the respective hamlets the use of open area for public convenience is avoided and it is very good proposal in view of health condition Each container toilet contained 5 seats for ladies and 5 seats for gents with all facilities like lighting and water supply.” - Physical Progress: 100%
- Project End Date: 11 Oct 2018
Sanitation –Buckle Canal screening
- Name of the Project: Sanitation –Buckle Canal screening
- Project cost (Rs.in Cr): 0.23
- Description:
On Provision of the screens in buckle odai the floating materials can be removed effectively and free water flow is assured and environment will be made clean. - Physical Progress: 100%
- Project End Date: 11 Oct 2018
Sanitation – Purchase of Tipper capacity 3.2 cum -10 nos
- Name of the Project: sanitation – Purchase of Tipper capacity 3.2 cum -10 nos
- Project cost (Rs.in Cr): 0.66
- Description:
“To mobilize the primary collection activities around the city in better manner. To improve the cleanliness of city and elemination of health hazards.” - Physical Progress: 100%
- Project End Date: 31 May 2019
E-Toilet
Categories
E-Toilet
- Name of the Project: E-Toilet
- Project cost (Rs.in Cr): 1.28
- Description:
The use of E-toilets are hygenic and no health hazards are anticipated. And it is a latest improvement and also it occupies minimum space and it warrents less maintanence, hence it is prioritized. - Physical Progress: 100%
- Project End Date: 08 Nov 2018
LED smart lights Phase II
Categories
LED smart lights Phase II
- Name of the Project: LED smart lights Phase II
- Project cost (Rs.in Cr): 3.92
- Description:
To construct the formation of orderly lighting arrangements in the traffic roads with eco friendly energy savings LED light and reduce the lighting polution. - Physical Progress: 100%
- Project End Date: 15 Oct 2020
Pearl Beach Road development and Kisok shop arrangemnets
- Name of the Project: Pearl Beach Road development and Kisok shop arrangemnets
- Project cost (Rs.in Cr): 0.94
- Description:
“The following improvements are programmed under smart city scheme for the effective use of public a) Providing CC pavements at Scatting yard b) Construction of Strom water drain at North beach road c) Providing Kiosk shop at Pearl beach d) Improvement of Pearl beach at North beach road” - Physical Progress: 100%
- Project End Date: 30 Jun 2020
Muthu Nagar Beach LED Fittings,providing UG cables and Highmast Light arrangements
- Name of the Project: Muthu Nagar Beach LED Fittings,providing UG cables and Highmast Light arrangements
- Project cost (Rs.in Cr): 0.59
- Description:
By securing the Muthu Nagar Park for the convineance of public entertinment including safety measures. - Physical Progress: 100%
- Project End Date: 30 Nov 2019
Smart Water Supply –Improvement of existing D system
- Name of the Project: Smart Water Supply –Improvement of existing D system
- Project cost (Rs.in Cr): 4.13
- Description:
Refer clause 2.4 & 2.5 in Smartcity Guidelines . - Physical Progress: 100%
- Project End Date: 31 Mar 2020