Author: xlmsmartcity

Badminton play ground with Gym at 5 Locations

Categories
OnGoing Projects

Badminton play ground with Gym at 5 Locations

  • Name of the Project: Badminton play ground with Gym at 5 LOocations
  • Project cost (Rs.in Cr): 6.25
  • Description:
    Construction of Badminton Court with indoor stadium and Smart Fitness Centre at Corporation area of 5 Locations in 1)Sundaravel puram. 2)Muthammal colony, 3)Pullthottam, 4) GLR, 5)Ashok Nagar.
  • Physical Progress: 35%
  • Project End Date: 30 Apr 2022

Construction of City Convention Centre near VVD OHT

Categories
OnGoing Projects

Construction of City Convention Centre near VVD OHT

  • Name of the Project: Construction of City Convention Centre near VVD OHT
  • Project cost (Rs.in Cr): 10.76
  • Description:
    It is proposed to construct Convention Centre of Overall Site area 1912 Sq.m (0.47 Acre) with Basement floor area 936 Sq.m, which has Parking which occupies 39 No of Two Wheelers and 21 Cars and Ground floor area 936 Sqm, which includes Kitchen, Store room, dining and Rest Room for Ladies and Gents. First floor aren 936 Sq.m which includes Green Room with attached toilet facility, Store room, Stage and seating capacity of 364 Numbers. Second floor area 444 Sq.m which includes Balcony of seating capacity 166 Numbers. Head Room area 480 Sq.m
  • Physical Progress: 43%
  • Project End Date: 30 Apr 2022

Construction of Chidambaram Nagar Shopping Mall

Categories
OnGoing Projects

Construction of Chidambaram Nagar Shopping Mall

Name of the Project: Construction of Chidambaram Nagar Shopping Mall

Project cost (Rs.in Cr): 15.62

Description:

It is proposed to construct Commercial Complex of Overall Site area 2947 Sq.m (0.73 Acre) with Basement floor area 1551 Sq.m, which has Parking which occupies 68 No of Two Wheelers and 33 Cars and Ground floor area 1446 Sq.m, which includes 15 No of Shops of varying size and Rest Room for Ladies and Gents. First floor area 1446 Sq.m which includes 17 No of Shops of varying size and Rest Room for Ladies and Gents, Second floor area 1446 Sq.m which includes 8 No of Shops of varying size, Restaurant with Kitchen attached, Boutique, Game arena and Rest Room for Ladies and Gents and Third floor area 1446 Sq.m which includes 2 No of Theatre of varying size having seating capacity of 580 seats and Food court with Kitchen attached.

Physical Progress: 34%

Project End Date: 07 Aug 2022

Redevelopment of Old Bus Stand

Categories
OnGoing Projects

Redevelopment of Old Bus Stand

Name of the Project: Redevelopment of Old Bus Stand

Project cost (Rs.in Cr): 55.67

Description:

It is proposed to construct Bus Terminal Development, Public Transport Improvement and transit hub of Overall area 3.36 acres with Ground floor area (Build up) of 13359 Sq.m and Ground floor area (Commercial) of 2295.52 Sq.m which includes Department office 1 Nos, other menities 16 Nos and ATM 2 Nos. Number of Bus Bays has given 29 Nos. First Floor . commercial area 2295.52 Sq.m and Parking area 2865.23 Sq.m which occupies 384 No of Two Wheelers and also second & third floor commercial area 2295.52 Sq.m and Parking area 2865.23 Sq.m which occupies 384 No of Two Wheelers and Fourth Floor Area 1864.18 Sq.m

Physical Progress: 80%

Project End Date: 30 Apr 2022

Storm water drain for Flood Mitigation

Construction of Storm Water Drain –ABD area – Phase II

Categories
OnGoing Projects

Construction of Storm Water Drain –ABD area – Phase II

Name of the Project: Construction of Storm Water Drain –ABD area – Phase II

Project cost (Rs.in Cr): 81.36

Description:

“1. Providing total length of 4711m of Storm Water Drain Along south cotton road (Joins to George Road), Drain along North Raja Street, Drain Along East Coast Road joins to Sea, Along Victoria Extension road & Branch Joined to George Road (Left & Right side of Road), Along Devispuram Road to Buckal Canal, Joins to SBI colony main Drain and Along Devispuram and Disposed to Buckal Canal . 2.Providing total length of 6974m of Strom Water Drain Along cross road from Palayamkottai road to Buckal Canal, Teachers Colony and Disposed Buckal Canal, Teachers Colony Main Road and Disposed to Buckal Canal, Along Millerpuram Main Road and Disposed to Buckal Canal, Along TMB Colony Main Road and Disposed to Buckal Canal, Along Millerpuram East Main Road and Disposed to Buckal Canal. 3.Providing total length of 7010m of Strom Water Drain from New colony to Sea (Via George Road road), Geetha Jeevan Nagar to Sea “

Physical Progress: 95%

Project End Date: 30 Apr 2022

Muthu Nagar Beach Development

Categories
OnGoing Projects

Muthu Nagar Beach Development

Name of the Project: Muthu Nagar Beach Development –

Project cost (Rs.in Cr): 4.67

Description

The following provision are made for development of parks. Compound wall, security room,Toilet arrangements, Lighting facilities,Sitting benches,Foot path, Play field arrangements, Green space development, Water supply and Electrical arrangements ,CCTV camera and parking facilities.

Physical Progress: 89%

Project End Date: 30 Mar 2022

Smart Schools- 5 Nos

Categories
OnGoing Projects

Smart Schools- 5 Nos

Name of the Project: Smart Schools- 5 Nos

Project cost (Rs.in Cr): 8.62

Description:

A smart school is – as its name suggests – different from a traditional school. This is a kind of school where advanced equipment and technology are used to take the educational process forward. The main idea is to provide the students with a learning experience that is a lot better than what may otherwise have been possible. The idea of the project was to implement Smart Schools equipped with School Management System, Learning Management System, Safety Management, Classroom Infrastructure which leads to significant improvement in quality of education. In order to needs of the corporation, redevolpment of five municipal corporation schools was converted in to smart schools with necessary infrastructure.

Physical Progress: 98%

Project End Date:15 Mar 2022

UGSS-Internal Plumbing

Categories
OnGoing Projects

UGSS-Internal Plumbing

Name of the Project
UGSS-Internal Plumbing

Project cost (Rs.in Cr)
11.17

Description
Thoothukudi UGSS scheme was Sanctioned by GOI for 1072.00 lakhs and work was executed by TWAD board . It is proposed to internal plumbing arrangements for UGS HSC Connection from property to boundary at thoothukkudi corporation areas.In this scheme laying of sewage pipe line connected with manhole and providing HSC from manhole to property boundary area also executed.Main source of the STP collected through manhole from individual HSC.

Physical Progress
40%

Project End Date
30 Jun 2022

Multi Level Car Parking (Jeyaraj Road near Flower Market)

Categories
OnGoing Projects

Multi Level Car Parking (Jeyaraj Road near Flower Market)

Name of the Project
Multi Level Car Parking (Jeyaraj Road near Flower Market)

Project cost (Rs.in Cr)
10.57

Description
It is proposed to construct Multi Level Car Parking with the following provision are made in Parking area, Toilet arrangements, lighting facilities, internal roads, lift, Rental shops and water supply arrangements etc., in this work.

Physical Progress
98%

Project End Date
15 Mar 2022